Eastern Wind Data Set

The Eastern Wind Integration Data Set was designed to help energy professionals perform wind integration studies and estimate power production from hypothetical wind power plants in the United States.

Access the Eastern Wind Integration Data Set Resources

Methodology

The Eastern Wind Integration Data Set consists of 3 years (2004–2006) of 10-minute wind speed and plant output values for 1,326 simulated wind power plants as well as next-day, 6-hour, and 4-hour forecasts for each plant. AWS Truepower created the data set with oversight and assistance from NREL.

After testing various mesoscale models, AWS Truepower settled on the MASS v.6.8 model to generate the wind data for the Eastern Wind Integration and Transmission Study. The model is initialized with input from the National Centers for Environmental Prediction/National Center for Atmospheric Research Global Reanalysis data set and assimilates both surface and rawindsonde data. The model used a nested grid scheme, with the final output resolution of 2 kilometers (km).

Wind power plant locations were determined using a proprietary AWS Truepower wind speed map of the study area along with 10 years of speed distributions previously computed by AWS Truepower. The wind resource at each cell was computed by combining these data sets with a composite turbine power curve. Wind power plants were then created by combining cells with close proximity and similar wind characteristics (subject to environmental, topographic, and other exclusions). Size and state-by-state distribution of wind power plants were controlled to give a diverse selection of plants. (For example, it was necessary to reduce the minimum capacity factor threshold to get enough plants in Connecticut, Rhode Island, New Jersey, and Delaware.)

The wind speed and power output time series for each wind power plant were computed by combining the mesoscale grid output with the composite turbine power curves, the list of cells contained in each plant, and other data. Adjustments were made for model biases, wake losses, the impact of gusts, availability, and other factors.

For a description of the overall project and more information about the modeling and inputs, read AWS Truepower's final report .

Site Selection

Land-based sites are actually simulated wind power plants composed of many nearby grid points that have similar wind characteristics. Sites range from 5 km2 to 160 km2, and maximum power output ranges from 100 megawatts (MW) to 1,435 MW. (Data from the individual grid points and the shape and layout of the sites are not available.) The site screening process excluded areas of open water, wetlands, parks, steep slopes, and nonpublic federal land. Airports and developed areas, along with buffer zones surrounding them, were also excluded.

The final site list contains 1,326 sites totaling 580 gigawatts (GW). The bulk of the sites fall between 100 MW and 600 MW. A smaller number (150) of "megasites" with rated capacities exceeding 1,000 MW were also chosen. All of these are in the Great Plains. A separate screening with a lower capacity factor threshold was performed for Connecticut, Rhode Island, New Jersey, and Delaware, with 30 sites selected in these states.

Offshore sites were chosen from a 2-km grid, wherein each grid point represented 20 MW of offshore wind capacity. Selected grid points were at least 8 km from shore and in water no deeper than 30 meters. A total of 4,948 sites in the Atlantic Ocean and four of the five Great Lakes were selected.

Wind Power Plant Output

Wind power plant output time-series values were computed by summing the contributions of each grid cell in the site. Three composite power curves (computed by averaging two or three power curves from commercial turbines) were available, and the choice of power curve was based on the average wind speed at the site. Adjustments were made for model biases, wake losses, wind gusts, turbine and plant availability, and other factors.

Forecasts

AWS Truepower produced hourly forecasts for three time horizons: next-day, 6-hour, and 4-hour. Each set of forecasts was synthesized by running a statistical forecast synthesis tool written by AWS Truepower called SynForecast. This tool uses actual forecasts and observed plant output to develop a set of transition probabilities that are then applied stepping forward in time from a random starting point in a process known as a Markov chain.

Data Update

The Eastern Wind Integration Data Set, originally developed as part of the Eastern Wind Integration and Transmission Study, was updated in June 2012 for use in the Eastern Renewable Generation Integration Study. The update was necessary to correct a discontinuity in aggregate wind power profiles at 12-hour intervals.

As part of the wind data synthesis procedure, observed data were assimilated into the weather simulation at 12-hour intervals, which caused the data discontinuity. The problem was identified during the Eastern Wind Integration and Transmission Study and partially fixed. The discontinuity was not significant in individual wind power plant profiles; however, it was more prominent in aggregations of wind power plant profiles. Because much of the statistical analysis in the Eastern Renewable Generation Integration Study will be performed on aggregations, it was necessary to develop and implement a fix.

Although the primary goal of the update was to mitigate the 12-hour discontinuity in aggregate profiles, the wind power conversion was also updated to better reflect future wind turbine technology. The 12-hour discontinuity was addressed by a technique that adjusted the correlated component of the wind power fluctuations by adding a proportion of the adjustment to each individual site. It was applied on a state-by-state basis. The updated wind power conversion incorporated new composite power curves that use larger wind turbines.

The wind power hourly forecasts were also updated based on the new synthesized 10-minute wind power profiles. In general, the same methodology was used to generate these forecasts as was used in the original Eastern Wind Integration and Transmission Study wind database.

For more information, see the report Updated Eastern Interconnect Wind Power Output and Forecasts for ERGIS.